Auditor General: MVR 136 million paid up front for cancelled housing and water projects has not been recovered
An audit of the construction and housing ministry's spending from 2018 to 2023 says 76% of the money paid in advance on 25 cancelled projects was never recovered. It also says re-awarding seven projects cost MVR 112 million more, and a MVR 59 million parking system brought no benefit.