TES2019W073 Procurement of Design, Build and Operate of a Waste to Energy Facility at K.Thilafushi

Procurement No TES/2019/W-073. This page is a restatement of the official record, so verify against the source links in the sidebar.

Awarded to
USD 304,574,286.89 ≈ MVR 4,696,535,504 at 15.42
1278 days for Design and Build and 15 years for Operation Service · awarded ⚑ 2021-07-11 by Ministry of Environment, Climate Change and Technology

⚑ Note: the awarded date published by the source, 2021-07-11, is in the future. This is shown exactly as published. It's most likely a mistyped year on the ministry's end, and hasn't been corrected here.

The contest

28 parties registered (pq) · 19 pq applications received · 5 Pass/Fail Remarks bids received k.thilafushi. Prices and results exactly as printed in the official award summary.

#BidderPrice DurationResultRemarks
1 Joint Venture of Techcross Water & Energy Inc. And GS KRW Engineering & Construction Corp.1 MVR 236,130,644.00 Pass CNY 117,312,018.00 CNY 117,312,018.00
2 Urbaser S.A.U. MVR 503,288,814.75 Pass AWARDED.
3 Joint Venture of China Enfi CNY Engineering Corporation and Babcock & Wilcox Beijing Company Ltd. MVR 136,914,000.00 Pass
4 Joint Venture of Hitachi Zosen Corporation and JGC Corporation Fail
5 Joint Venture of China National Electric Engineering Co Ltd and China Western Power Co Ltd Fail
6 LG Hitachi Water Solution Co. Ltd., was renamed Did not submit
7 Evaluated Bid Price Joint Venture of Techcross Water & Energy Inc. GS Engineering & Construction Corp. USD 211,756,919.48
8 Urbaser S.A.U. USD 183,049,729.90
9 Joint Venture of China Enfi Engineering Corporation and Babcock & Wilcox Beijing Company Ltd. USD 275,984,917.33

How it was decided

Selection based on
Substantially responsive Lowest Evaluated Bidder. The Evaluated Bid Price is determined as the sum of the Design-Build price and the
Procurement Description Pre-qualification Summary
Design, Build and Operate of a Waste to Energy Facility at Name of Applicants
1. JV of LG Hitachi Water Solution
Co. Ltd., GS Engineering & Construction Corporation and Lotus
2. JV of China ENFI Engineering
Co. Limited and Babcock & Wilcox Beijing Company Ltd.,
3. Suez International JV Suez
India Pvt. Limited
4. JV of China National Electric
Engineering Co. Ltd., and China Western Power Co. Limited
5. JV of Hitachi Zosen Corporation 6. URBASER S.A.U.
and JGC Corporation
JV of SINOHYDRO Corporation 7.
Limited, CHONGCOING SANFENG ENVIRONMENT
SANFENG CONVANTA
ENVIRONMENTAL INDUSTRIAL CO. LTD.
8. Chosun Refractories Eng. Co.
Ltd.
9. JV of China State Construction 10. Ramky Enviro Engineers Limited
Engineering Corp. Ltd. and Zhejiang Weiming Environment Protection
Engineering Co. Ltd. GROUP CORP and CHONGOING
Pass Pre-qualified. Pass Pre-qualified. Pass Pre-qualified. Pass Pre-qualified. Pass Pre-qualified. Pass Pre-qualified. Fail Fail
Co. Limited.
Fail Fail
NTB Endorsed Date
11th July 2021
ADB No-objection Date
05th August 2021

How it unfolded

22nd May 2019
Invitation released on
04th August 2019
Technical Bid opening held on
01st September 2020
Technical Bid opening held on
22nd April 2021
Financial Bid opening held on
⚑ 2021-07-11
Awarded