Construction of Police Station building at L.Fonadhoo
Procurement No TES/2021/W-164-R02. This page is a restatement of the official record, so verify against the source links in the sidebar.
⚑ Note: the awarded date published by the source, 2022-08-11, is in the future. This is shown exactly as published. It's most likely a mistyped year on the ministry's end, and hasn't been corrected here.
The contest
6 parties registered · 5 bids received. Prices and results exactly as printed in the official award summary.
| # | Bidder | Price | Duration | Result | Remarks |
|---|---|---|---|---|---|
| 1 | Fast Line Pvt Ltd AWARDED | MVR 11,354,746.99 | 365 days | Pass | — |
| 2 | Venza Company Pvt Ltd | MVR 12,621,124.53 | 365 days | Pass | — |
| 3 | FEDO PVT LTD | MVR 13,747,978.71 | 365 days | Pass | — |
| 4 | Unique Choice Pvt Ltd | MVR 13,214,974.71 | 365 days | Fail | Does not meet Historical Contract Non-Performance Requirement |
| 5 | Holistic Maldives Pvt Ltd | MVR 13,317,978.75 | 365 days | Fail | Does not meet Historical Contract Non-Performance, Financial and Experience Requirement |
How it was decided
Selection based on
Substantially responsive Lowest Evaluated Bidder.
How it unfolded
29th June 2022
Invitation released on
7th July 2022
Bid opening held on
⚑ 2022-08-11
Awarded
Tender history
⚑ Flagged: 2 records in the public tender listing share this procurement number once special characters are ignored, so no single tender can be identified with confidence. Candidates: