TES/2019/W-177 - Construction of 6 Classroom at S.Atoll School
Procurement No TES/2019/W-177. This page is a restatement of the official record, so verify against the source links in the sidebar.
⚑ Note: the awarded date published by the source, 2020-02-27, is in the future. This is shown exactly as published. It's most likely a mistyped year on the ministry's end, and hasn't been corrected here.
The contest
10 parties registered · 8 bids received. Prices and results exactly as printed in the official award summary.
| # | Bidder | Price | Duration | Result | Remarks |
|---|---|---|---|---|---|
| 1 | Maris Construction Pvt Ltd | — | 300 Days | Fail | Does not meet Eligibility requirements. |
| 2 | MIMS Construction Pvt Ltd | — | 365 Days | Pass | — |
| 3 | Nooradheen Investment Pvt Ltd | — | 206 Days | Pass | Awarded |
| 4 | SJ Construction Pvt Ltd | — | 364 Days | Pass | — |
| 5 | SNR Company Pvt Ltd | — | 125 Days | Fail | Does not meet Financial & Experience requirements. |
| 6 | Afami Maldives Pvt Ltd | — | 330 Days | Pass | — |
| 7 | Ascend Contractors Pvt Ltd | — | 270 Days | Fail | Does not meet Experience requirements. |
| 8 | ECS Engineering Pvt Ltd | Did not submit | |||
How it was decided
Procurement Description
Construction of 06 Classrooms at S.Atoll School
Selection based on
Substantially responsive Lowest Evaluated Bidder.
How it unfolded
31st December 2019
Invitation released on
30th January 2020
Bid opening held on
⚑ 2020-02-27
Awarded