The Public Ledger

Loading data…

← All awarded projects

TES/2020/W-001 Construction of Terminal Building and Fire Building at Hoarafushi Airport

Procurement No TES/2020/W-001. This page is a restatement of the official record, so verify against the source links in the sidebar.

Awarded to
MVR 11,532,293.09
300 Days · awarded ⚑ 2020-03-08 by Regional Airports

⚑ Note: the awarded date published by the source, 2020-03-08, is in the future. This is shown exactly as published. It's most likely a mistyped year on the ministry's end, and hasn't been corrected here.

The contest

9 parties registered · 8 bids received. Prices and results exactly as printed in the official award summary.

#BidderPrice DurationResultRemarks
1 Inoca Pvt Ltd AWARDED MVR 11,532,293.09 300 days Pass
2 Nasa Link Pvt Ltd MVR 11,902,285.6 180 days Pass
3 Wave Length Pvt Ltd MVR 12,495,694.15 180 days Pass
4 Amin Construction Pvt Ltd MVR 16,572,607.73 180 days Pass
5 Uni Engineering Pvt Ltd MVR 19,573,005.67 300 days Fail Does not meet experience requirements
6 Afami Maldives Pvt Ltd MVR 19,605,704.23 450 days Pass
7 Q1 Maldives Pvt Ltd MVR 22,968,971.56 365 days Fail Does not meet the financial requirements
8 Precision Engineering Services Pvt Ltd MVR 23,683,378.07 240 days Fail Does not meet the financial and experience requirements

How it was decided

Procurement Description
Construction of Terminal Building and Fire Building
Selection based on
Substantially responsive Lowest Evaluated Bidder.

How it unfolded

9th January 2020
Invitation released on
10th February 2020
Bid opening held on
⚑ 2020-03-08
Awarded