Construction of 04 Classroom and Multipurpose Hall at GDH.Vaadhoo Jamaluddin School - Retender
Procurement No TES/2021/W-100-R01. This page is a restatement of the official record, so verify against the source links in the sidebar.
⚑ Note: the awarded date published by the source, 2022-10-26, is in the future. This is shown exactly as published. It's most likely a mistyped year on the ministry's end, and hasn't been corrected here.
The contest
9 parties registered · 6 bids received. Prices and results exactly as printed in the official award summary.
| # | Bidder | Price | Duration | Result | Remarks |
|---|---|---|---|---|---|
| 1 | Holistic Maldives Pvt Ltd | MVR 10,899,788.72 | 365 Days | Fail | Failed from Financial & Experience Requirement. |
| 2 | North Coast Contractors Private Limited AWARDED | MVR 13,309,603.96 | 290 Days | Pass | — |
| 3 | Pawarey Investment Pvt Ltd | MVR 13,045,490.58 | 365 Days | Fail | Failed from Financial Requirement. |
| 4 | T.A Construction & Trading Pvt Ltd | MVR 16,937,517.92 | 180 Days | Fail | Failed from Financial Requirement. |
| 5 | Yes Maldives Pvt Ltd | MVR 18,301,102.08 | 365 Days | Pass | — |
| 6 | Swift Engineering Pvt Ltd | MVR 19,932,870.13 | 360 Days | Fail | Failed from eligibility criteria. |
How it was decided
Procurement Description
Construction of 04 Classrooms and Multipurpose Hall at GDH.Vaadhoo
Selection based on
Substantially responsive Lowest Evaluated Bidder.
How it unfolded
23rd August 2021
Invitation released on
6th September 2021
Bid opening held on
⚑ 2022-10-26
Awarded