Costruction of 12 Classroom at K.Maafushi School
Procurement No TES/2021/W-162. This page is a restatement of the official record, so verify against the source links in the sidebar.
⚑ Note: the awarded date published by the source, 2022-02-23, is in the future. This is shown exactly as published. It's most likely a mistyped year on the ministry's end, and hasn't been corrected here.
The contest
8 parties registered · 6 bids received. Prices and results exactly as printed in the official award summary.
| # | Bidder | Price | Duration | Result | Remarks |
|---|---|---|---|---|---|
| 1 | Two A Company Pvt Ltd | MVR 11,506,793.15 | 360 Days | Fail | Failed from Financial Requirement. |
| 2 | Evosun Maldives Pvt Ltd | MVR 12,105,094.96 | 360 Days | Fail | Contract Non-Performance & Financial Requirement. |
| 3 | North Coast Contractors Pvt Ltd | MVR 15,153,693.31 | 300 Days | Fail | Failed from Historical Contract Non-Performance. |
| 4 | Maziya Construction Pvt Ltd | MVR 15,651,651.04 | 365 Days | Fail | Failed from Historical Contract Non-Performance. |
| 5 | Micron Pvt Ltd AWARDED | MVR 16,398,938.46 | 365 Days | Pass | — |
| 6 | Afami Maldives Pvt Ltd | MVR 23,060,597.74 | 365 Days | Fail | Failed from Historical Contract Non-Performance. |
How it was decided
Procurement Description
Construction of 12 Classroom at K.Maafushi School
Selection based on
Substantially responsive Lowest Evaluated Bidder.
How it unfolded
23rd November 2021
Invitation released on
23rd December 2021
Bid opening held on
⚑ 2022-02-23
Awarded