The contest
3 parties registered · 3 bids received. Prices and results exactly as printed in the official award summary.
| # | Bidder | Price | Duration | Result | Remarks |
|---|---|---|---|---|---|
| 1 | LF Construction Pvt Ltd | MVR 9,298,064.05 | 365 Days | Fail | to Public Finance Regulations therefore cannot award a contract carried out by the Government of Maldives during |
| 2 | Aim Construction Pvt Ltd AWARDED | MVR 11,341,575.60 | 325 Days | Pass | (23-Nov-2021 to 22-Nov-2022) |
| 3 | Mims Construction Pvt Ltd | MVR 11,496,729.64 | 365 Days | Fail | — |
How it was decided
Procurement Description
Construction of Multi - Purpose Hall at R.Innamaadhoo school
Selection based on
Substantially responsive Lowest Evaluated Bidder.
How it unfolded
08th September 2021
Invitation released on
04th October 2021
Bid opening held on
⚑ 2021-04-18
Awarded