TES/2019/W-155- Construction of Holy Quran Building at Gn.Fuvahmulah
Procurement No TES/2019/W-155. This page is a restatement of the official record, so verify against the source links in the sidebar.
⚑ Note: the awarded date published by the source, 2020-01-16, is in the future. This is shown exactly as published. It's most likely a mistyped year on the ministry's end, and hasn't been corrected here.
The contest
10 parties registered · 6 bids received. Prices and results exactly as printed in the official award summary.
| # | Bidder | Price | Duration | Result | Remarks |
|---|---|---|---|---|---|
| 1 | Maris Construction Pvt.Ltd AWARDED | MVR 6,214,108.26 | 300 days | Pass | — |
| 2 | A man Maldives Pvt.Ltd | MVR 7,193,993.16 | 365 days | Pass | — |
| 3 | Nuga Construction Pvt.Ltd | MVR 7,943,933.52 | 210 days | Pass | — |
| 4 | SJ Construction Pvt.Ltd | MVR 9,061,582.64 | 364 days | Pass | — |
| 5 | Amin Construction Pvt.Ltd | MVR 9,090,421.49 | 240 days | Pass | — |
| 6 | Con Biz Pvt.Ltd | MVR 17,688,420.92 | 223 days | Fail | Does not comply with required NCR grading. |
How it was decided
Procurement Description
Construction of Center for Holy Quran Building at Gn.Fuvahmulah
Selection based on
Substantially responsive Lowest Evaluated Bidder.
How it unfolded
25th November 2019
Invitation released on
9th January 2020
Bid opening held on
⚑ 2020-01-16
Awarded