TES/2019/W-155- Construction of Holy Quran Building at Gn.Fuvahmulah

Procurement No TES/2019/W-155. This page is a restatement of the official record, so verify against the source links in the sidebar.

Awarded to
MVR 6,214,108.26
300 Days · awarded ⚑ 2020-01-16 by Ministry of Islamic Affairs

⚑ Note: the awarded date published by the source, 2020-01-16, is in the future. This is shown exactly as published. It's most likely a mistyped year on the ministry's end, and hasn't been corrected here.

The contest

10 parties registered · 6 bids received. Prices and results exactly as printed in the official award summary.

#BidderPrice DurationResultRemarks
1 Maris Construction Pvt.Ltd AWARDED MVR 6,214,108.26 300 days Pass
2 A man Maldives Pvt.Ltd MVR 7,193,993.16 365 days Pass
3 Nuga Construction Pvt.Ltd MVR 7,943,933.52 210 days Pass
4 SJ Construction Pvt.Ltd MVR 9,061,582.64 364 days Pass
5 Amin Construction Pvt.Ltd MVR 9,090,421.49 240 days Pass
6 Con Biz Pvt.Ltd MVR 17,688,420.92 223 days Fail Does not comply with required NCR grading.

How it was decided

Procurement Description
Construction of Center for Holy Quran Building at Gn.Fuvahmulah
Selection based on
Substantially responsive Lowest Evaluated Bidder.

How it unfolded

25th November 2019
Invitation released on
9th January 2020
Bid opening held on
⚑ 2020-01-16
Awarded