Construction of 06 Classroom Block at Th.Burunee School
Procurement No TES/2021/W - 014. This page is a restatement of the official record, so verify against the source links in the sidebar.
⚑ Note: the awarded date published by the source, 2021-05-06, is in the future. This is shown exactly as published. It's most likely a mistyped year on the ministry's end, and hasn't been corrected here.
The contest
13 parties registered · 10 bids received. Prices and results exactly as printed in the official award summary.
| # | Bidder | Price | Duration | Result | Remarks |
|---|---|---|---|---|---|
| 1 | Jiaz Maldives Pvt Ltd | MVR 5,736,190.95 | 195 Days | Fail | Does not meet experience requirements. |
| 2 | Mims Construction Pvt Ltd AWARDED | MVR 5,834,841.27 | 360 Days | Pass | — |
| 3 | LF Construction Pvt Ltd | MVR 6,107,357.69 | 300 Days | Pass | — |
| 4 | Pensare Maldives Pvt Ltd | MVR 6,166,323.74 | 260 Days | Fail | Does not meet experience requirements. |
| 5 | Micron Pvt Ltd | MVR 6,946,943.09 | 240 Days | Fail | Does not meet experience requirements. |
| 6 | Nasa Link Pvt Ltd | MVR 6,994,537.26 | 360 Days | Pass | — |
| 7 | Afami Maldives Pvt Ltd | MVR 7,358,039.50 | 360 Days | Fail | Does not meet experience requirements. |
| 8 | A Man Maldives Pvt Ltd. | MVR 7,395,857.15 | 365 Days | Pass | — |
| 9 | Fenmuli Construction Pvt Ltd | MVR 7,992,988.48 | 364 Days | Fail | Does not meet financial and experience requirements. |
| 10 | W Construction Company Pvt Ltd | MVR 8,896,942.03 | 300 Days | Fail | Does not meet experience requirements. |
How it was decided
Procurement Description
Construction of 6 Classrooms at Th. Burunee School
Selection based on
Substantially responsive Lowest Evaluated Bidder.
How it unfolded
11th February 2021
Invitation released on
8th March 2021
Bid opening held on
⚑ 2021-05-06
Awarded