Construction of Proposed 18 Classrooms at S. Hithadhoo Sharafudheen School
Procurement No TES/2021/W-013. This page is a restatement of the official record, so verify against the source links in the sidebar.
⚑ Note: the awarded date published by the source, 2021-03-31, is in the future. This is shown exactly as published. It's most likely a mistyped year on the ministry's end, and hasn't been corrected here.
The contest
11 parties registered · 10 bids received. Prices and results exactly as printed in the official award summary.
| # | Bidder | Price | Duration | Result | Remarks |
|---|---|---|---|---|---|
| 1 | Inoca Pvt ltd AWARDED | MVR 11,604,370.79 | 365 days | Pass | — |
| 2 | Venza Company Pvt Ltd | MVR 12,544,058.85 | 361 days | Pass | — |
| 3 | BAPC & Trading Pvt.Ltd | MVR 12,765,334.47 | 340 days | Pass | — |
| 4 | Swift Engineering Pvt.Ltd | MVR 13,219,020.86 | 360 days | Pass | — |
| 5 | Timeless Group Pvt.Ltd | MVR 13,243,781.21 | 365 days | Pass | — |
| 6 | LF Construction Pvt Ltd | MVR 13,833,040.44 | 360 days | Pass | — |
| 7 | SJ Trade Pvt.Ltd | MVR 14,267,560.35 | 365 days | Pass | — |
| 8 | Nooradheen Investment | MVR 14,944,759.93 | 365 days | Fail | Failed in minimum Experience Requirement |
| 9 | Rainbow Construction Pvt.Ltd | MVR 18,362,164.41 | 250 days | Fail | Did not Register |
| 10 | W Construction Company Pvt Ltd | MVR 18,811,732.09 | 365 days | Fail | Failed in minimum Experience Requirement |
How it was decided
Procurement Description
Construction of S. Hithadhoo Sharafudheen School 18 classroom
Selection based on
Substantially responsive Lowest Evaluated Bidder.
How it unfolded
11th February 2021
Invitation released on
8th March 2021
Bid opening held on
⚑ 2021-03-31
Awarded